Where is Tallentire Hill up to?

Each status below comes from a named source and date.

Onshore wind · England, North West

Planning

Planning
Granted
4 Feb 2011
DESNZ REPD, 3 Aug 2026
Construction
Built
6 Jul 2012
DESNZ REPD, 3 Aug 2026
Operational status
Operational
9 Jul 2013
DESNZ REPD, 3 Aug 2026

Connection

Connection
Onshore wind project, epj_a1d31622bed92ad2

Measures

Rated power
12.0 MW
Connection capacity
Not published
Storage energy
Not published