Battery · England, Eastern
Planning
- Planning
- Granted
- 14 Jul 2025
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_a2aaf00a1f5c8b05
Measures
- Rated power
- 0.2 MW
- Connection capacity
- Not published
- Storage energy
- Not published