Where is JJ Foodservice, Lilac Grove - Solar Panels up to?

Each status below comes from a named source and date.

Solar PV · England, East Midlands

Planning

Planning
Application submitted
22 May 2026
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_a2b14971e7c3440e

Measures

Rated power
0.4 MW
Connection capacity
Not published
Storage energy
Not published