Where is Carcant Windfarm up to?
Each status below comes from a named source and date.
Onshore wind · Scotland
Planning
- Planning
- Granted
- 15 Sep 2006
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 Apr 2010
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 2 Nov 2010
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_a5f045f07062d422
Measures
- Rated power
- 6.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published