Onshore wind · Scotland

Planning

Planning
Granted
22 Jun 2012
DESNZ REPD, 3 Aug 2026
Construction
Built
30 Oct 2013
DESNZ REPD, 3 Aug 2026
Operational status
Operational
1 Mar 2015
DESNZ REPD, 3 Aug 2026

Connection

Connection
Onshore wind project, epj_a75ff3ce91e71e67

Measures

Rated power
3.2 MW
Connection capacity
Not published
Storage energy
Not published