Projects
Where is Fletchers Bakeries Limited, Clay Wheels Lane - Solar Panels up to?
Each status below comes from a named source and date.
Solar PV · England, Yorkshire and Humber
Planning
- Planning
- Application submitted
- 10 Aug 2023
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_a7b4950025e0141c
Measures
- Rated power
- 0.6 MW
- Connection capacity
- Not published
- Storage energy
- Not published