Solar PV · England, East Midlands
Planning
- Planning
- Granted
- 7 Mar 2024
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_a8305616299b6204
Measures
- Rated power
- 34.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published