Where is Berry Court Solar Farm - energy storage up to?

Each status below comes from a named source and date.

Battery · England, South East

Planning

Planning
Granted
DESNZ REPD, 3 Aug 2026
Construction
Built
DESNZ REPD, 3 Aug 2026
Operational status
Operational
1 Dec 2017
DESNZ REPD, 3 Aug 2026

Connection

Connection
Battery project, epj_a8e02dd45152c6d0

Measures

Rated power
1.0 MW
Connection capacity
Not published
Storage energy
Not published