Projects
Where is Land North of the Wood at Averill Farm up to?
Each status below comes from a named source and date.
Solar PV · England, East Midlands
Planning
- Planning
- Granted
- 21 Oct 2015
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 15 Jan 2016
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 15 Mar 2016
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_ab0440e1027c3e6a
Measures
- Rated power
- 5.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published