Grid

Projects

Projects

Where is Llangwyryfon up to?

Each status below comes from a named source and date.

Onshore wind · Wales

Planning

Planning
Granted
1 Mar 2003
DESNZ REPD, 3 Aug 2026
Construction
Built
DESNZ REPD, 3 Aug 2026
Operational status
Operational
1 Feb 2004
DESNZ REPD, 3 Aug 2026

Connection

Connection
Onshore wind project, epj_aeaa619656c75b03

Measures

Rated power
9.4 MW
Connection capacity
Not published
Storage energy
Not published