Where is Parkhill Farm, Letham Grange - Solar Farm up to?

Each status below comes from a named source and date.

Solar PV · Scotland

Planning

Planning
Granted
19 Dec 2023
DESNZ REPD, 3 Aug 2026
Construction
Not started
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_af4efc2f96ad231c

Measures

Rated power
18.0 MW
Connection capacity
Not published
Storage energy
Not published