Where is Land at Upper Clayhill Farm up to?

Each status below comes from a named source and date.

Solar PV · England, South East

Planning

Planning
Granted
18 Dec 2014
DESNZ REPD, 3 Aug 2026
Construction
Built
20 Aug 2015
DESNZ REPD, 3 Aug 2026
Operational status
Operational
16 Dec 2015
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_b07fe7eb6c2c2a1c

Measures

Rated power
4.9 MW
Connection capacity
Not published
Storage energy
Not published