Where is Hyndburn Wind Farm Extension up to?
Each status below comes from a named source and date.
Onshore wind · England, North West
Planning
- Planning
- Granted
- 26 Jun 2015
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_b4434b1a1a13cc3c
Measures
- Rated power
- 8.2 MW
- Connection capacity
- Not published
- Storage energy
- Not published