Where is Wally Corner Landfill Site up to?

Each status below comes from a named source and date.

Solar PV · England, South East

Planning

Planning
Granted
29 Sep 2015
DESNZ REPD, 3 Aug 2026
Construction
Built
15 Oct 2016
DESNZ REPD, 3 Aug 2026
Operational status
Operational
15 Mar 2017
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_b6394f3d1c788eab

Measures

Rated power
7.0 MW
Connection capacity
Not published
Storage energy
Not published