Projects
Where is Frying Down Copse Solar Farm up to?
Each status below comes from a named source and date.
Solar PV · England, South East
Planning
- Planning
- Granted
- 13 May 2011
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 16 Apr 2012
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_b767106536c296ad
Measures
- Rated power
- 5.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published