Grid

Projects

Projects

Where is High Parkfoot Farm up to?

Each status below comes from a named source and date.

Solar PV · England, North West

Planning

Planning
Granted
21 Jul 2022
DESNZ REPD, 3 Aug 2026
Construction
Not started
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_b97cc2897e04f0d3

Measures

Rated power
20.0 MW
Connection capacity
Not published
Storage energy
Not published