Where is Pant y wal up to?
Each status below comes from a named source and date.
Onshore wind · Wales
Planning
- Planning
- Granted
- 4 May 2011
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 Apr 2012
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 1 Jun 2013
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_bb229adc78fb5434
Measures
- Rated power
- 25.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published