Where is Strichen North BESS up to?

Each status below comes from a named source and date.

Battery · Scotland

Planning

Planning
Abandoned
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
NESO TEC register, 13 Oct 2026

Connection

Connection
Agreement held
31 Oct 2033
NESO TEC register, 13 Oct 2026

Measures

Rated power
25.0 MW
Connection capacity
25.0 MW
Storage energy
Not published