Onshore wind · Scotland
Planning
- Planning
- Granted
- 24 Dec 2009
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 31 Dec 2012
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_be168f54d3b0c2fa
Measures
- Rated power
- 4.5 MW
- Connection capacity
- Not published
- Storage energy
- Not published