Projects
Where is The Adidas Centre, Hazel Grove - Solar Array up to?
Each status below comes from a named source and date.
Solar PV · England, North West
Planning
- Planning
- Granted
- 1 Feb 2023
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_be67c3bbfaba8a8e
Measures
- Rated power
- 0.6 MW
- Connection capacity
- Not published
- Storage energy
- Not published