Solar PV · England, South West
Planning
- Planning
- Granted
- 7 May 2014
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 15 Oct 2015
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 1 Feb 2017
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_be99295ed09e254e
Measures
- Rated power
- 4.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published