Projects
Where is Devon Wood up to?
Each status below comes from a named source and date.
Onshore wind · Scotland
Planning
- Planning
- Refused
- 22 Nov 2012
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_bf4bb90f93beb1b2
Measures
- Rated power
- 12.5 MW
- Connection capacity
- Not published
- Storage energy
- Not published