Onshore wind · England, Yorkshire and Humber
Planning
- Planning
- Granted
- 31 Jan 2007
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 1 Feb 2008
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_c1047c1278d38afd
Measures
- Rated power
- 1.3 MW
- Connection capacity
- Not published
- Storage energy
- Not published