Offshore wind · Scotland, Offshore
Planning
- Planning
- Granted
- 18 Nov 2011
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 8 Oct 2013
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 31 Mar 2014
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Offshore wind project, epj_c1799db11f07dc7d
Measures
- Rated power
- 7.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published