Where is Persley Croft - Battery Storage up to?
Each status below comes from a named source and date.
Battery · Scotland
Planning
- Planning
- Granted
- 29 Aug 2024
- DESNZ REPD, 3 Aug 2026
- Construction
- Under construction
- NESO TEC register, 13 Oct 2026
- Operational status
- Commissioning
- NESO TEC register, 13 Oct 2026
Connection
- Connection
- Gate 2, Agreement held
- 30 Jul 2026
- NESO TEC register, 13 Oct 2026
Measures
- Rated power
- 49.9 MW
- Connection capacity
- 50.0 MW
- Storage energy
- Not published