Where is St Nicholas Court Farm (AD) up to?

Each status below comes from a named source and date.

Anaerobic digestion · England, South East

Planning

Planning
Granted
26 Sep 2013
DESNZ REPD, 3 Aug 2026
Construction
Built
31 Mar 2014
DESNZ REPD, 3 Aug 2026
Operational status
Operational
1 Dec 2014
DESNZ REPD, 3 Aug 2026

Connection

Connection
Anaerobic digestion project, epj_c3b9faef1b50d0f0

Measures

Rated power
1.2 MW
Connection capacity
Not published
Storage energy