Where is Carn Nicholas Farm up to?
Each status below comes from a named source and date.
Solar PV · Wales
Planning
- Planning
- Granted
- 14 Dec 2015
- DESNZ REPD, 3 Aug 2026
- Construction
- Under construction
- 28 Dec 2018
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_c3c8999dd8e870c5
Measures
- Rated power
- 5.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published