Where is Ratty's Lane Sustainable Energy Facility (ACT) up to?
Each status below comes from a named source and date.
Advanced conversion · England, Eastern
Planning
- Planning
- Granted
- 26 Mar 2012
- DESNZ REPD, 3 Aug 2026
- Construction
- Under construction
- 25 Jul 2016
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Advanced conversion project, epj_c42cf3a97df4bc95
Measures
- Rated power
- 9.6 MW
- Connection capacity
- Not published
- Storage energy
- Not published