Projects
Where is Land SW of Shilton Cottage up to?
Each status below comes from a named source and date.
Battery · Scotland
Planning
- Planning
- Granted
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 1 Jan 2022
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_c4539bd3f2f29be4
Measures
- Rated power
- 29.9 MW
- Connection capacity
- Not published
- Storage energy
- Not published