Projects
Where is Jutes Lane, Weatherlees Hill - Solar Panels up to?
Each status below comes from a named source and date.
Solar PV · England, South East
Planning
- Planning
- Granted
- 15 Nov 2024
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_c8f16d8da1497269
Measures
- Rated power
- 3.3 MW
- Connection capacity
- Not published
- Storage energy
- Not published