Projects
Where is Catsbrain Farm - Battery Storage up to?
Each status below comes from a named source and date.
Battery · England, South West
Planning
- Planning
- Granted
- 3 Oct 2023
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_ca852fa54f31be72
Measures
- Rated power
- 30.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published