Projects
Where is Severn Trent Water - Stoke Bardolph Wind Turbine up to?
Each status below comes from a named source and date.
Onshore wind · England, East Midlands
Planning
- Planning
- Granted
- 19 Sep 2013
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 15 Mar 2015
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 15 Dec 2015
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_cbd4e5a063d4308c
Measures
- Rated power
- 1.5 MW
- Connection capacity
- Not published
- Storage energy
- Not published