Where is Yorkshire Botanicals - Biomass Boiler up to?

Each status below comes from a named source and date.

Biomass · England, Yorkshire and Humber

Planning

Planning
Granted
15 Nov 2022
DESNZ REPD, 3 Aug 2026
Construction
Not started
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Biomass project, epj_ce8dd40e86a1533b

Measures

Rated power
5.0 MW
Connection capacity
Not published
Storage energy
Not published