Projects
Where is Pancross & Oaklands Solar Farm up to?
Each status below comes from a named source and date.
Battery · Wales
Planning
- Planning
- Granted
- 23 May 2024
- DESNZ REPD, 3 Aug 2026
- Construction
- Under construction
- 1 Oct 2025
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_cea834785680e5a4
Measures
- Rated power
- 50.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published