Solar PV · England, Eastern
Planning
- Planning
- Granted
- 19 Nov 2014
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 Sep 2015
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 17 Oct 2015
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_d2ed84d285a4dbda
Measures
- Rated power
- 15.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published