Where is Manor Farm - Pertenhall up to?

Each status below comes from a named source and date.

Solar PV · England, Eastern

Planning

Planning
Granted
19 Nov 2014
DESNZ REPD, 3 Aug 2026
Construction
Built
1 Sep 2015
DESNZ REPD, 3 Aug 2026
Operational status
Operational
17 Oct 2015
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_d2ed84d285a4dbda

Measures

Rated power
15.0 MW
Connection capacity
Not published
Storage energy
Not published