Solar PV · England, South West
Planning
- Planning
- Granted
- 9 Jul 2013
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 23 Feb 2014
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 3 Nov 2014
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_d60e7185aebd0ffc
Measures
- Rated power
- 6.3 MW
- Connection capacity
- Not published
- Storage energy
- Not published