Projects
Where is Energy Recovery Facility South Street up to?
Each status below comes from a named source and date.
Advanced conversion · Scotland
Planning
- Planning
- Refused
- 24 Mar 2021
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Advanced conversion project, epj_d65283fe78ba52bf
Measures
- Rated power
- 12.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published