Projects
Where is Tollgate Farm Battery Storage up to?
Each status below comes from a named source and date.
Battery · England, Eastern
Planning
- Planning
- Granted
- 22 Jan 2019
- DESNZ REPD, 3 Aug 2026
- Construction
- Under construction
- 1 Feb 2022
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_d77a6e58e6e513f2
Measures
- Rated power
- 49.5 MW
- Connection capacity
- Not published
- Storage energy
- Not published