Battery · England, South East
Planning
- Planning
- Revised
- 15 Nov 2024
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_d789e61cb4e3aa84
Measures
- Rated power
- 0.2 MW
- Connection capacity
- Not published
- Storage energy
- Not published