Where is Hazlehead up to?

Each status below comes from a named source and date.

Onshore wind · England, Yorkshire and Humber

Planning

Planning
Granted
8 Mar 2007
DESNZ REPD, 3 Aug 2026
Construction
Built
1 Aug 2010
DESNZ REPD, 3 Aug 2026
Operational status
Operational
16 Dec 2011
DESNZ REPD, 3 Aug 2026

Connection

Connection
Onshore wind project, epj_d8f5d6e41e89f791

Measures

Rated power
6.0 MW
Connection capacity
Not published
Storage energy
Not published