Projects
Where is K3 CHP Facility (Kemsley EfW) up to?
Each status below comes from a named source and date.
Energy from waste · England, South East
Planning
- Planning
- Granted
- 13 Jul 2010
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 30 Sep 2016
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 21 Jul 2020
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Energy from waste project, epj_da27cc7366dbbba8
Measures
- Rated power
- 49.9 MW
- Connection capacity
- Not published
- Storage energy
- Not published