Where is West Mains of Kinblethmont up to?

Each status below comes from a named source and date.

Solar PV · Scotland

Planning

Planning
Granted
4 Sep 2015
DESNZ REPD, 3 Aug 2026
Construction
Built
15 Feb 2016
DESNZ REPD, 3 Aug 2026
Operational status
Operational
31 Mar 2016
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_dba2be4c651db6bb

Measures

Rated power
5.0 MW
Connection capacity
Not published
Storage energy
Not published