Where is Sober Hill Wind Farm up to?

Each status below comes from a named source and date.

Onshore wind · England, Yorkshire and Humber

Planning

Planning
Granted
19 Mar 2010
DESNZ REPD, 3 Aug 2026
Construction
Built
1 Mar 2012
DESNZ REPD, 3 Aug 2026
Operational status
Operational
1 Sep 2013
DESNZ REPD, 3 Aug 2026

Connection

Connection
Onshore wind project, epj_dd936bc632ec6bee

Measures

Rated power
15.0 MW
Connection capacity
Not published
Storage energy
Not published