Where is Kiln Park Holiday Centre, Marsh Road - Solar Photovoltaic Panels up to?
Each status below comes from a named source and date.
Solar PV · Wales
Planning
- Planning
- Granted
- 21 Nov 2023
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_de330fd0bd2a4115
Measures
- Rated power
- 0.2 MW
- Connection capacity
- Not published
- Storage energy
- Not published