Where is Fforch Nest Wind Farm pt1 up to?
Each status below comes from a named source and date.
Onshore wind · Wales
Planning
- Planning
- Granted
- 4 May 2011
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 30 Oct 2011
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 24 May 2013
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_dedd07e5bed7e1c0
Measures
- Rated power
- 10.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published