Onshore wind · Wales

Planning

Planning
Granted
4 May 2011
DESNZ REPD, 3 Aug 2026
Construction
Built
30 Oct 2011
DESNZ REPD, 3 Aug 2026
Operational status
Operational
24 May 2013
DESNZ REPD, 3 Aug 2026

Connection

Connection
Onshore wind project, epj_dedd07e5bed7e1c0

Measures

Rated power
10.0 MW
Connection capacity
Not published
Storage energy
Not published