Onshore wind · England, East Midlands
Planning
- Planning
- Application submitted
- 15 Apr 2026
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_df6b2f4aecce29af
Measures
- Rated power
- 0.5 MW
- Connection capacity
- Not published
- Storage energy
- Not published