Projects
Where is Winscales Moor up to?
Each status below comes from a named source and date.
Onshore wind · England, North West
Planning
- Planning
- Granted
- 20 Jun 2007
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 Dec 2008
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 1 May 2009
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_e0db8ef905bb5526
Measures
- Rated power
- 6.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published