Projects
Where is Land at Bolsover Moor Quarry up to?
Each status below comes from a named source and date.
Solar PV · England, East Midlands
Planning
- Planning
- Granted
- 29 Sep 2015
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 4 Jan 2017
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 1 Mar 2017
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_e29956ae4c8d2dcb
Measures
- Rated power
- 5.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published