Projects
Where is Funtley Refuse Tip up to?
Each status below comes from a named source and date.
Solar PV · England, South East
Planning
- Planning
- Permission expired
- 28 Aug 2016
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_e2a3455e2ff277f8
Measures
- Rated power
- 10.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published