Solar PV · England, Yorkshire and Humber

Planning

Planning
Granted
26 Feb 2025
DESNZ REPD, 3 Aug 2026
Construction
Not started
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_e2bb491c3608b01e

Measures

Rated power
30.4 MW
Connection capacity
Not published
Storage energy
Not published